Drywall was delivered about a week later than promised but even then, the workers who were to install it didn't show up all week long. On Friday, after they said they were on their way, and still didn't show up, they said they would work through the weekend in order to catch up.
I wasn't sure what "catch up" meant until today. Tomorrow an inspection of the drywall installation is scheduled and they will need to have it all nailed into place by then.
 |
| Garage |
 |
| Kitchen |
 |
| Under-stair closet |
They have made good progress but here and there are problems that need to be fixed. For example, they covered the opening for the slide from the stair landing (I don't know why they wouldn't recognize a slide entrance on a stair landing first thing!).
Also, Lisa's bedroom has two closets -- one on each side of the window.
The opening of one closet was left to be framed with casing for a closet door.
 |
| Lisa's left closet |
The other was covered with drywall like a doorway that wouldn't have a door.
 |
| Lisa's right closet |